Sandhya P
DAY FOUR// The hanging chairs were placed on the wall to create shelving and a coat rack in the reception area.
Posted 19 May 2015 11:35
DAY THREE// WEDNESDAY// to create a more precise base we began to create a drawing in AutoCAD. It was here that we could measure the angles and lengths of the hangers.
Posted 19 May 2015 11:29
Kitchen space in the making// green wall // small table // wheelbarrow chairs
Posted 15 May 2015 09:01
"Borrowing" materials to make tables of different heights easily. Desks//Coffee tables
Posted 15 May 2015 08:59
DAY FOUR// Metal base for the hanger screen is being constructed in the Metal Workshop.The metal will create stability and hopefully hold the structure upright. Created in response to our previous attempt which fell over.
Posted 14 May 2015 18:06
FOREGROUND// New hanger screen// Double curved for extra balance
BACKGROUND// Previous hanger screen lying in it's grave
BACKGROUND// Previous hanger screen lying in it's grave
Posted 14 May 2015 17:48
After the collapse, we tried to create a more stable structure // widening the surface area and increase the amount of poles
Posted 14 May 2015 17:47
From the morning of DAY 2// TRIAL 2// image taken previous to it's collapse
Posted 14 May 2015 17:44
TEAMWORK// Sanding wood// Drilling the green wall// Constructing the hanger wall
Posted 14 May 2015 17:42
The Borrowers HQ - a room borrowed from the St James Building - Grade II listed building in Oxford Street, Manchester, England, completed in 1912.